How did Moorhouse Coating transform the 500-bed hospital?
Quick Answer: Moorhouse Coating transformed an 850,000 square foot, 500-bed hospital using antimicrobial and zero-VOC coatings while maintaining 100% operational uptime. ICRA Level IV containment, phased night and weekend work, patient-area scheduling, and infection-control coordination completed the six-month project on time and under budget with minimal patient disruption.
Regional Medical Center Complete Transformation
How we painted an 850,000 sq ft hospital while maintaining 100% operational uptime
The Client
Regional Medical Center
- 500-bed Level I Trauma Center
- Serving 2.5 million residents
- 24/7 emergency services
- Joint Commission accredited
- 12,000+ employees
Project Goals
- • Modernize facility appearance
- • Implement antimicrobial coatings
- • Improve wayfinding and color coding
- • Maintain 100% operational uptime
- • Complete within 6-month window
Regional Medical Center - Main Campus
Challenges & Solutions
Challenge: 24/7 Operations
Our Solution:
Phased approach with night/weekend work in critical areas
Challenge: Infection Control
Our Solution:
ICRA Level IV protocols with negative air pressure containment
Challenge: Patient Sensitivity
Our Solution:
Zero-VOC paints and odor mitigation strategies
Challenge: Regulatory Compliance
Our Solution:
Joint Commission and CMS standards exceeded
Project Timeline
Phase 1
6 weeksEmergency Department & ICU
Night work only, full containment
Phase 2
8 weeksPatient Rooms (Floors 2-5)
Rolling schedule, 20 rooms at a time
Phase 3
6 weeksOperating Theaters
Weekend work during scheduled downtime
Phase 4
4 weeksCommon Areas & Lobbies
Section-by-section with wayfinding maintained
Project Results
Patient Complaints
No disruption to patient care throughout project
Under Budget
Completed $125,000 under original estimate
ICRA Compliance
Exceeded all infection control requirements
Technologies & Products Used
Antimicrobial Paint
EPA-registered antimicrobial additives
Zero-VOC Coatings
No odor, safe for occupied spaces
Scrubbable Finish
Withstands hospital-grade cleaners
Color-Coded System
Improved wayfinding and department ID
Key Takeaways
-
Operational Continuity is Possible
With proper planning and phasing, large healthcare facilities can be painted without disrupting patient care
-
ICRA Protocols are Essential
Strict adherence to infection control standards protects vulnerable patients
-
Communication is Critical
Daily coordination with facility management ensures smooth project flow
-
Specialized Products Matter
Antimicrobial and zero-VOC coatings are worth the investment in healthcare settings