Walmart Supercenter Dallas
180,000 sq ft Retail Renovation with Zero Business Disruption
Complete interior and exterior transformation of major retail location completed in just 3 weeks using overnight work schedule, advanced coating systems, and meticulous coordination with store operations.
Project Overview
This Walmart Supercenter in Dallas, Texas serves over 5,000 customers daily and operates 24 hours a day, 7 days a week. The facility required a comprehensive interior and exterior refresh as part of Walmart's nationwide store modernization initiative while maintaining continuous operations without any revenue loss.
Our team was selected for this high-profile retail renovation based on our proven expertise in retail store painting with minimal business disruption. The project demanded precise coordination with store management, overnight stocking crews, and department managers to ensure seamless execution.
Working exclusively during overnight hours from 10 PM to 6 AM, our specialized retail crews completed 180,000 square feet of painting and epoxy floor coatings in just 3 weeks. The store opened for business each morning with zero evidence of construction activity—a testament to our operational excellence and commitment to customer experience.
Challenges & Solutions
Challenges
- • Maintaining 24/7 store operations serving 5,000+ customers daily during renovation
- • Coordinating work around continuous grocery stocking and overnight inventory operations
- • Managing odor-free environment for fresh food departments and customer areas
- • Working around existing fixtures, shelving, and merchandise displays without damage
- • Meeting strict Walmart brand standards and department-specific color schemes
- • Completing project within aggressive 3-week deadline during holiday season prep
- • Ensuring safety compliance with customers and staff in active work zones
- • Protecting high-traffic floor areas requiring specialized epoxy coating systems
Solutions
- ✓ 100% night shift work schedule from 10 PM to 6 AM with complete daily cleanup
- ✓ Close coordination with store management and overnight stocking teams for zone access
- ✓ Zero-VOC and low-odor paint systems safe for food service environments
- ✓ Detailed protection protocols for all fixtures, merchandise, and customer touchpoints
- ✓ Professional color matching to Walmart's corporate brand guidelines
- ✓ Multi-crew deployment with specialized teams for different departments and tasks
- ✓ Comprehensive safety barriers and signage systems during active work periods
- ✓ Fast-cure epoxy systems for high-traffic entrances and checkout areas
Technical Specifications
3-Week Execution Timeline
Phase 1: Week 1
7 nightsBack-of-House Areas & Preparation (Nights 1-7)
- ▸ Storage rooms, receiving areas, and employee break rooms completed first
- ▸ Established workflow patterns with minimal customer-facing disruption
- ▸ Epoxy floor coating installation in receiving dock and storage zones
- ▸ Team coordination protocols finalized with store management
Phase 2: Week 2
7 nightsSales Floor Departments & High-Traffic Zones (Nights 8-14)
- ▸ Systematic department-by-department painting during overnight hours
- ▸ Grocery, electronics, apparel, and home goods sections completed
- ▸ Fast-cure epoxy installation at main entrance and checkout zones
- ▸ Daily quality control inspections before 6 AM store opening
Phase 3: Week 3
7 nightsFinal Details & Exterior Touch-ups (Nights 15-21)
- ▸ Customer service areas, pharmacy, and specialty departments finished
- ▸ Exterior entrance refresh and signage area painting completed
- ▸ Final walkthrough and touch-up work throughout entire facility
- ▸ Project completed 2 days ahead of schedule with zero punch list items
Retail Operations Coordination
Maintaining seamless 24/7 retail operations required detailed coordination and flexible scheduling to work around customer traffic, inventory management, and store activities.
Store Hours Management
Coordinated all work during 10 PM - 6 AM window with complete area restoration before opening. Implemented containment systems allowing customers to shop normally during day shifts.
Inventory & Stocking Coordination
Worked around overnight stocking crews with detailed zone scheduling. Maintained access corridors for inventory flow while painting adjacent areas.
Safety & Customer Protection
Used professional barriers and clear signage during work hours. All equipment removed and areas cleaned before store opening with zero customer disruptions.
Department Manager Communication
Daily briefings with department managers on schedule and progress. Flexible approach allowed immediate adjustments for special events or promotional displays.
"Moorhouse Coating transformed our entire Supercenter in just three weeks without disrupting a single day of business. Their overnight crews were professional, efficient, and meticulous about cleanup. We never received a customer complaint, and the store looks absolutely fantastic. The project finished ahead of schedule, which was critical for our holiday season preparation. We've already contracted them for our other Dallas-area locations."
Results & Impact Metrics
Project Impact
The Walmart Supercenter renovation delivered exceptional results that exceeded client expectations while maintaining continuous business operations. The comprehensive transformation improved the shopping environment, enhanced brand consistency, and positioned the store for increased customer satisfaction.
Operational Excellence
- ✓ Completed 2 days ahead of schedule
- ✓ Zero customer complaints throughout project
- ✓ 100% Walmart brand standard compliance
- ✓ Zero safety incidents or violations
Business Benefits
- ✓ No lost revenue during renovation period
- ✓ Enhanced customer shopping experience
- ✓ Improved employee morale and satisfaction
- ✓ 10-year warranty on all coating systems
Related Services
Retail Store Painting
Specialized painting services for retail environments with minimal disruption.
Epoxy Floor Coatings
High-performance floor coating systems for commercial applications.
24/7 Painting Services
Round-the-clock painting to accommodate your business schedule.
Related Case Studies

Retail Store Renovation
Multi-location retail painting program with consistent brand standards.

National Retail Chain 50 Stores
Large-scale retail renovation program across 50 store locations.

Amazon Distribution Center
Warehouse and distribution facility coating with rapid turnaround.
Ready to Transform Your Retail Space?
Get a free consultation and project estimate from our retail painting experts.